Eilert Construction Company had a contract starting April 2018, to construct a $42,000,000 building that is expected to be completed in September 2019, at an estimated cost of $38,500,000. At the end of 2018, the costs to date were $17,710,000 and the estimated total costs to complete had not changed. The progress billings during 2018 were $8,400,000 and the cash collected during 2018 was $5,600,000. Eilert uses the percentage-of-completion method. [ What makes-up Construction in Process