What is your standard deviation of demand during lead time if your average lead time = 5 days, standard deviation of demand = 4, average demand is 12, and standard deviation of lead time is 1.2 days.

Respuesta :

Answer:

4.47

Explanation:

The computation of the standard deviation of lead time is shown below:

= √lead time × standard deviation of demand

= √ 5 days × 4

= √20

= 4.47

We simply applied the above formula to determine the standard deviation of demand during lead time

Hence, all the other items would be ignored