The total completion time is 25 days. task a is planned to take seven days. task b is planned to take five days. task c is planned to take eight days. the tasks have a serial relationship. how much slack does the project have?

Respuesta :

The project currently has Positive 5 days slack.

Times needed for task A = 7 days
Times needed for task B = 5 days
Times needed for task C = 8 days

Total predicted days = 20 days

Since the project is required to be completed in 25 days, the company has 25 days - 20 days = 5 days positive